Put the following rig components and stages in right rigging up order.

Читайте также:
  1. A dream in the hands of the right person is a winner every time
  2. A few common expressions are enough for most telephone conversations. Practice these telephone expressions by completing the following dialogues using the words listed below.
  3. A) Answer the following questions about yourself.
  4. A) Identify each of the electronic components below and draw their circuit symbol in the space provided.
  5. A) The advertisement in A-column has been mixed and, to arrange them in the right sequence, consult the advertisement in B-coIumn.
  6. A) Think of ONE noun to complete all of the following collocations
  7. A. Starting Off on the Right Foot

 

 


Read the following texts and match them with above-mentioned rig components and rigging up stages. Fill in the chart.

 


Rig component Description Function Additional information
       

Part II. Rig Systems

A rotary rig's main job is to make hole. To make hole, the drilling crew places a bit on bottom, then the driller rotates it and pumps drilling mud to it. A rig needs a multitude of equipment to make these operations happen. A first look at all the gear on a drilling rig can over­whelm you. It is, however, easy to un­derstand a rig's components if you divide them into systems: power, hoist­ing, rotating, and circulating.

       
 
1. Power system  
 
2. Hoisting system



Diesel engine 1 Drawworks

Diesel engine 2 Cathead

Diesel engine 3 Blocks and drilling lines

4. Circulating system
3. Rotating system   ting system
Electric motors

Swivel Drilling mud

Kelly Mud pits

Rotary table Mud pumps

Top drive Rotary hose

Drill pipe Return line

Drill bit Shale shaker

 

1. Read the text “Power system” and fill in the missing words from the box. There is one extra word.

Power system

Without 1. power nothing on a rig operates. Machinery must have an energy source to make it go. On virtually every drilling rig, the power comes from internal-combustion engines, which are called prime movers. Further, they often use diesel 2.. Because of the way diesel engines operate, they deliver more turning force, or torque, than gasoline engines. As a result, many industries, including the 3. _industry, use diesels.

A 4. may need from two to four prime movers, depending on its size. The bigger the rig, the deeper it can drill and the more power it needs. Thus, big rigs have three or four prime movers. Together, they develop 4,500 horsepower (about 3,300 kilowatts) or more. In comparison, a powerful car engine may put out only 300 horsepower (220 kilowatts) or so; most develop even less.

This power must 5. to the rig's components to make them work. For example, at the same time as the rotary table needs power to turn the bit, the mud pump needs power to 6. drilling mud. What is more, to provide maximum power to a component, the 7. must also be able to combine the power of two or more engines. Two common methods transfer power on today's rigs and allow the driller to combine engine power: mechanical transmission and electrical transmission.

transfer; mix; drilling; fuelt; circulate; driller; rig; power

 

(Baker R. “A Primer of Oil Well Drilling”, 2001, Austin, Texas)


Дата добавления: 2015-10-26; просмотров: 134 | Нарушение авторских прав


Читайте в этой же книге: Acquisition of Seismic Data | Form nouns from the following verbs. | The life of a well includes several stages. Put the following key words according to the stages and describe each of them. | Discuss what well types can be applied during the following processes. Define the logical order. | Rotary system components | Put the following circulating system components in a right order to make the system work. | Terms and Vocabulary | Terms and Vocabulary | Give an explanation to the following purposes of the pipeline system. | Pipeline Construction |