Студопедия
Случайная страница | ТОМ-1 | ТОМ-2 | ТОМ-3
АвтомобилиАстрономияБиологияГеографияДом и садДругие языкиДругоеИнформатика
ИсторияКультураЛитератураЛогикаМатематикаМедицинаМеталлургияМеханика
ОбразованиеОхрана трудаПедагогикаПолитикаПравоПсихологияРелигияРиторика
СоциологияСпортСтроительствоТехнологияТуризмФизикаФилософияФинансы
ХимияЧерчениеЭкологияЭкономикаЭлектроника

Risk management

Читайте также:
  1. Approaches to Management
  2. Bass Management or Redirection
  3. Business and Management Personal Statement
  4. Business and Management/economics ps
  5. D.2.1 - Project management
  6. Doctrine şi şcoli de management.
  7. Economics & Management Personal Statement

There are two steps in risk management: risk assessment and mitigation. Risk assessment is concerned with analysing threat s and weaknesses that have been or would be introduced as a result of a service change.

A risk occurs when a threat can exploit a weakness. The likelihood of threats exploiting a weakness, and the impact if they do, are the fundamental factors in determining risk.

The risk management formula is simple but very powerful:

Risk = Likelihood x Impact

Obviously, the introduction of new threats and weaknesses increases the likelihood of a threat exploiting a weakness. Placing greater dependence on a service or component increases the impact if an existing threat exploits an existing weakness within the service. These are just a couple of examples of how risk may increase as a result of a service change.

It is a clear requirement that a proposed service change must assess the existing risks within a service and the predicted risks following implementation of the change.

If the risk level has increased then the second stage of risk management is used to mitigate the risk. In the examples given above mitigation may include steps to eliminate a threat or weakness and using disaster recovery and backup techniques to increase the resilience of a service on which the organization has become more dependent.

Following mitigation the risk level is re-assessed and compared with the original. This second assessment and any subsequent assessments are in effect determining residual risk – the risk that remains after mitigation. Assessment of residual risk and associated mitigation continues to cycle until risk is managed down to an acceptable level.

The guiding principle here is that either the initial risk assessment or any residual risk level is equal to or less than the original risk prior to the service change. If this is not the case then evaluation will recommend rejection of proposed service change, or back out of an implemented service change.

The approach to risk representation recommended here takes a fundamentally different approach. Building on the work of Drake (2005a, 2005b) this approach recognizes that risks almost always grow exponentially over time if left unmanaged, and that a risk that will not cause a loss probably is not worth worrying about too much.

It is therefore proposed that a stronger risk representation is as shown in Figure 4.35. Principally, this representation is intended to promote debate and agreement by stakeholders: is the risk positioned correctly in terms of time and potential or actual loss; could mitigation have been deployed later (e.g. more economically); should it have been deployed earlier (e.g. better protection); etc.

Figure 4.35 Example risk profile

Deviations – predicted vs actual performance

Once the service change passes the evaluation of predicted performance and actual performance, essentially as standalone evaluations, a comparison of the two is carried out. To have reached this point it will have been determined that predicted performance and actual performance are acceptable, and that there are no unacceptable risks. The output of this activity is a deviations report. For each factor in Table 4.14 the report states the extent of any deviation between predicted and actual performance.


Дата добавления: 2015-10-29; просмотров: 142 | Нарушение авторских прав


Читайте в этой же книге: Release design options and considerations | Designing release and release packages | Valuable release windows | Build and test prior to production | Service testing and pilots | Plan and prepare for deployment | Early life support | Inputs from Service Design | Types of testing | Process activities, methods and techniques |
<== предыдущая страница | следующая страница ==>
Verify test plan and test design| Establishing data and information management procedures

mybiblioteka.su - 2015-2024 год. (0.011 сек.)