Figure 4.32 Example of a validation and testing process
The testing process is shown schematically in Figure 4.32. The test activities are not undertaken in a sequence. Several activities may be done in parallel, e.g. test execution begins before all the test design is complete. The activities are described below.
Validation and test management
Test management includes the planning, control and reporting of activities through the test stages of Service Transition. These activities include:
Test management includes managing issues, mitigating risks and implementing changes identified from the testing activities as these can impose delays and create dependencies that need to be proactively managed.
Test metrics are used to measure the test process and manage and control the testing activities. They enable the test manager to determine the progress of testing, the earned value and the outstanding testing, and this helps the test manager to estimate when testing will be completed. Good metrics provide information for management decisions that are required for prioritization, scheduling and risk management. They also provide useful information for estimating and scheduling for future releases.
Plan and design test
Test planning and design activities start early in the service lifecycle and include: