Steps carried out 24.5
1. Establishment of base line 7.1 17.4
14.5
24.5 24.5
2. Setting out the right angle at the correct laugh and offer we checked the diagonals.
13.5
23.5
Figure 9: setting out operation
3. Setting the profiles boards of the trench foundation wall.
4. Establishment of profiles
5. Making of position of portion walls on the profile with lither mails and sow cuts
6. The stretched of building line through the nails and cornet pegs mark.
All setting out work have been carried manually for giving jobs Ngoma populations.