task С
Work H (6; 11) can be extended for more than 5 days, as it is not critical
Task D
Activity | Comes before | Duration | Crash Duration | Crash cost per day |
A | C | 4 days | 2 days | • |
B | F | 6 days | 3 days | $1,200 |
C | D.E | 6 days | 3 days | $900 |
D | G | 5 days | 2 days | $1,500 |
E | J | 6 days | 3 days | $2,800 $1,300 |
F | H | 9 days | 5 days | $1300 |
G | I | 4 days | 2 days | • |
H | L | 5 days | 3 days | $1,000 |
I | J | 4 days | 2 days | • |
J | K,L | 5 days | 2 days | $2,500 |
K | M | 7 days | 3 days | $3,500 |
L | M | 6 days | 3 days | $1,800 |
M | - | 3 days | 1 day | - |
Sum |
Paths FROM POINTS | Durations (max) |
A-C-D-G-I-J-K-M | 4+6+5+4+4+5+7+3=38 |
G-I-J-K-M | 4+4+5+7+3=23 |
I-J-K-M | 4+5+7+3=19 |
Activity | Duration | Crash Duration | Crash cost per day | Possible day to GAIN |
A | 4 days | 2 days | • | |
B | 6 days | 3 days | $1,200 | |
C | 6 days | 3 days | $900 | |
D | 5 days | 2 days | $1,500 | |
E | 6 days | 3 days | $2,800 $1,300 | |
F | 9 days | 5 days | $1300 | |
G | 4 days | 2 days | • | |
H | 5 days | 3 days | $1,000 | |
I | 4 days | 2 days | • | |
J | 5 days | 2 days | $2,500 | |
K | 7 days | 3 days | $3,500 | |
L | 6 days | 3 days | $1,800 | |
M | 3 days | 1 day | - | |
Critical Activity | Crash cost per day | Possible day to GAIN |
A | • | |
C | $900 | |
D | $1,500 | |
G | • | |
I | • | |
J | $2,500 | |
K | $3,500 | |
M | - | |
Other activity | ||
B | $1,200 | |
E | $2,800 $1,300 | |
F | $1300 | |
H | $1,000 | |
L | $1,800 |
We don’t know daily project costs, but if it will be $Z for example, we can do this:
Start from point A
Activity | Activity duration | Net savings | Project duration | |
Decrease (A) by 1 day | 4(3) days | +(Z-·) | ||
Decrease (A) by 1 day | 3(2) days | +(Z-·) | Activity (A) cannot be shortened anymore | |
Decrease (C) by 1 day | 6(5) days | +(Z-$900) | ||
Decrease (C) by 1 day | 5(4) days | +(Z-$900) | ||
Decrease (C) by 1 day | 4(3) days | +(Z-$900) | Activity (C) cannot be shortened anymore | |
Decrease (D) by 1 day | 5(4) days | +(Z-$1,500) | ||
Decrease (D) by 1 day | 4(3) days | +(Z-$1,500) | ||
Decrease (D) by 1 day | 3(2) days | +(Z-$1,500) | Activity (D) cannot be shortened anymore | |
Decrease (G) by 1 day | 4(3) days | +(Z-·) | ||
Decrease (G) by 1 day | 3(2) days | +(Z-·) | Activity (G) cannot be shortened anymore | |
Decrease (I) by 1 day | 4(3) days | +(Z-·) | ||
Decrease (I) by 1 day | 3(2) days | +(Z-·) | Activity (I) cannot be shortened anymore | |
Decrease (J) by 1 day | 5(4) days | +(Z-$2,500) | ||
Decrease (J) by 1 day | 4(3) days | +(Z-$2,500) | ||
Decrease (J) by 1 day | 3(2) days | +(Z-$2,500) | Activity (J) cannot be shortened anymore | |
Decrease (K) by 1 day | 7(6) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 6(5) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 5(4) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 4(3) days | +(Z-$3,500) | Activity (K) cannot be shortened anymore | |
Decrease (M) by 1 day | 3(2) days | +(Z-$1,800) | ||
Decrease (M) by 1 day | 2(1) days | +(Z-$1,800) | Desired project duration |
Net savings = (Z-·)*6 + (Z-$900)*3 +(Z-$1,500)*3 + (Z-$2,500)*3 + (Z-$3,500)*4 + (Z-$1,800)*2 =Z*21-(6*·+$2700+4500+7500+14000+3600)= Z*21-(6*·+$32300)
Start from point G:
Activity | Activity duration | Net savings | Project duration | |
Decrease (G) by 1 day | 4(3) days | +(Z-·) | ||
Decrease (G) by 1 day | 3(2) days | +(Z-·) | Activity (G) cannot be shortened anymore | |
Decrease (I) by 1 day | 4(3) days | +(Z-·) | ||
Decrease (I) by 1 day | 3(2) days | +(Z-·) | Activity (I) cannot be shortened anymore | |
Decrease (J) by 1 day | 5(4) days | +(Z-$2,500) | ||
Decrease (J) by 1 day | 4(3) days | +(Z-$2,500) | ||
Decrease (J) by 1 day | 3(2) days | +(Z-$2,500) | Activity (J) cannot be shortened anymore | |
Decrease (K) by 1 day | 7(6) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 6(5) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 5(4) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 4(3) days | +(Z-$3,500) | Activity (K) cannot be shortened anymore | |
Decrease (M) by 1 day | 3(2) days | +(Z-$1,800) | ||
Decrease (M) by 1 day | 2(1) days | +(Z-$1,800) | Desired project duration |
Net savings=(Z-·)*4+(Z-$2,500)*3+(Z-$3,500)*4+(Z-$1,800)*2=Z*13-(4*·+7500+14000+3600) = Z*13-(4*·+$25100)
Start from point I:
Activity | Activity duration | Net savings | Project duration | |
Decrease (I) by 1 day | 4(3) days | +(Z-·) | ||
Decrease (I) by 1 day | 3(2) days | +(Z-·) | Activity (I) cannot be shortened anymore | |
Decrease (J) by 1 day | 5(4) days | +(Z-$2,500) | ||
Decrease (J) by 1 day | 4(3) days | +(Z-$2,500) | ||
Decrease (J) by 1 day | 3(2) days | +(Z-$2,500) | Activity (J) cannot be shortened anymore | |
Decrease (K) by 1 day | 7(6) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 6(5) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 5(4) days | +(Z-$3,500) | ||
Decrease (K) by 1 day | 4(3) days | +(Z-$3,500) | Activity (K) cannot be shortened anymore | |
Decrease (M) by 1 day | 3(2) days | +(Z-$1,800) | ||
Decrease (M) by 1 day | 2(1) days | +(Z-$1,800) | Desired project duration |
Net savings = (Z-·)*2 + (Z-$2,500)*3 + (Z-$3,500)*4 + (Z-$1,800)*2 = Z*11-(2*·+7500+14000+3600) = Z*13-(4*·+$25100)
Дата добавления: 2015-07-18; просмотров: 101 | Нарушение авторских прав
<== предыдущая страница | | | следующая страница ==> |
Critical path: (0,1)(1,3)(3,5)(5,7)(7,8)(8,9)(9,10)(10,13)(13,14) – O1, A, C, D, G, I, J, K, M | | | ГАЙНСКОГО МУНИЦИПАЛЬНОГО РАЙОНА |