not a critical path

Читайте также:
  1. Critical path: (0,1)(1,3)(3,5)(5,7)(7,8)(8,9)(9,10)(10,13)(13,14) – O1, A, C, D, G, I, J, K, M

task С

Work H (6; 11) can be extended for more than 5 days, as it is not critical

 

Task D

Activity Comes before Duration Crash Duration Crash cost per day
A C 4 days 2 days
B F 6 days 3 days $1,200
C D.E 6 days 3 days $900
D G 5 days 2 days $1,500
E J 6 days 3 days $2,800 $1,300
F H 9 days 5 days $1300  
G I 4 days 2 days
H L 5 days 3 days $1,000
I J 4 days 2 days
J K,L 5 days 2 days $2,500
K M 7 days 3 days $3,500
L M 6 days 3 days $1,800
M - 3 days 1 day -
  Sum      

 

Paths FROM POINTS Durations (max)
A-C-D-G-I-J-K-M 4+6+5+4+4+5+7+3=38
G-I-J-K-M 4+4+5+7+3=23
I-J-K-M 4+5+7+3=19

 

Activity Duration Crash Duration Crash cost per day Possible day to GAIN
A 4 days 2 days  
B 6 days 3 days $1,200  
C 6 days 3 days $900  
D 5 days 2 days $1,500  
E 6 days 3 days $2,800 $1,300  
F 9 days 5 days $1300    
G 4 days 2 days  
H 5 days 3 days $1,000  
I 4 days 2 days  
J 5 days 2 days $2,500  
K 7 days 3 days $3,500  
L 6 days 3 days $1,800  
M 3 days 1 day -  
         

 

Critical Activity Crash cost per day Possible day to GAIN
A  
C $900  
D $1,500  
G  
I  
J $2,500  
K $3,500  
M -  
     
Other activity    
B $1,200  
E $2,800 $1,300  
F $1300    
H $1,000  
L $1,800  

 

We don’t know daily project costs, but if it will be $Z for example, we can do this:

Start from point A

 

Activity Activity duration Net savings Project duration  
Decrease (A) by 1 day 4(3) days +(Z-·)    
Decrease (A) by 1 day 3(2) days +(Z-·)   Activity (A) cannot be shortened anymore
Decrease (C) by 1 day 6(5) days +(Z-$900)    
Decrease (C) by 1 day 5(4) days +(Z-$900)    
Decrease (C) by 1 day 4(3) days +(Z-$900)   Activity (C) cannot be shortened anymore
Decrease (D) by 1 day 5(4) days +(Z-$1,500)    
Decrease (D) by 1 day 4(3) days +(Z-$1,500)    
Decrease (D) by 1 day 3(2) days +(Z-$1,500)   Activity (D) cannot be shortened anymore
Decrease (G) by 1 day 4(3) days +(Z-·)    
Decrease (G) by 1 day 3(2) days +(Z-·)   Activity (G) cannot be shortened anymore
Decrease (I) by 1 day 4(3) days +(Z-·)    
Decrease (I) by 1 day 3(2) days +(Z-·)   Activity (I) cannot be shortened anymore
Decrease (J) by 1 day 5(4) days +(Z-$2,500)    
Decrease (J) by 1 day 4(3) days +(Z-$2,500)    
Decrease (J) by 1 day 3(2) days +(Z-$2,500)   Activity (J) cannot be shortened anymore
Decrease (K) by 1 day 7(6) days +(Z-$3,500)    
Decrease (K) by 1 day 6(5) days +(Z-$3,500)    
Decrease (K) by 1 day 5(4) days +(Z-$3,500)    
Decrease (K) by 1 day 4(3) days +(Z-$3,500)   Activity (K) cannot be shortened anymore
Decrease (M) by 1 day 3(2) days +(Z-$1,800)    
Decrease (M) by 1 day 2(1) days +(Z-$1,800)   Desired project duration

 

Net savings = (Z-·)*6 + (Z-$900)*3 +(Z-$1,500)*3 + (Z-$2,500)*3 + (Z-$3,500)*4 + (Z-$1,800)*2 =Z*21-(6*·+$2700+4500+7500+14000+3600)= Z*21-(6*·+$32300)

 

Start from point G:

Activity Activity duration Net savings Project duration  
Decrease (G) by 1 day 4(3) days +(Z-·)    
Decrease (G) by 1 day 3(2) days +(Z-·)   Activity (G) cannot be shortened anymore
Decrease (I) by 1 day 4(3) days +(Z-·)    
Decrease (I) by 1 day 3(2) days +(Z-·)   Activity (I) cannot be shortened anymore
Decrease (J) by 1 day 5(4) days +(Z-$2,500)    
Decrease (J) by 1 day 4(3) days +(Z-$2,500)    
Decrease (J) by 1 day 3(2) days +(Z-$2,500)   Activity (J) cannot be shortened anymore
Decrease (K) by 1 day 7(6) days +(Z-$3,500)    
Decrease (K) by 1 day 6(5) days +(Z-$3,500)    
Decrease (K) by 1 day 5(4) days +(Z-$3,500)    
Decrease (K) by 1 day 4(3) days +(Z-$3,500)   Activity (K) cannot be shortened anymore
Decrease (M) by 1 day 3(2) days +(Z-$1,800)    
Decrease (M) by 1 day 2(1) days +(Z-$1,800)   Desired project duration

Net savings=(Z-·)*4+(Z-$2,500)*3+(Z-$3,500)*4+(Z-$1,800)*2=Z*13-(4*·+7500+14000+3600) = Z*13-(4*·+$25100)

 

Start from point I:

Activity Activity duration Net savings Project duration  
Decrease (I) by 1 day 4(3) days +(Z-·)    
Decrease (I) by 1 day 3(2) days +(Z-·)   Activity (I) cannot be shortened anymore
Decrease (J) by 1 day 5(4) days +(Z-$2,500)    
Decrease (J) by 1 day 4(3) days +(Z-$2,500)    
Decrease (J) by 1 day 3(2) days +(Z-$2,500)   Activity (J) cannot be shortened anymore
Decrease (K) by 1 day 7(6) days +(Z-$3,500)    
Decrease (K) by 1 day 6(5) days +(Z-$3,500)    
Decrease (K) by 1 day 5(4) days +(Z-$3,500)    
Decrease (K) by 1 day 4(3) days +(Z-$3,500)   Activity (K) cannot be shortened anymore
Decrease (M) by 1 day 3(2) days +(Z-$1,800)    
Decrease (M) by 1 day 2(1) days +(Z-$1,800)   Desired project duration

 

Net savings = (Z-·)*2 + (Z-$2,500)*3 + (Z-$3,500)*4 + (Z-$1,800)*2 = Z*11-(2*·+7500+14000+3600) = Z*13-(4*·+$25100)

 

 


Дата добавления: 2015-07-18; просмотров: 101 | Нарушение авторских прав


<== предыдущая страница | следующая страница ==>
Critical path: (0,1)(1,3)(3,5)(5,7)(7,8)(8,9)(9,10)(10,13)(13,14) – O1, A, C, D, G, I, J, K, M| ГАЙНСКОГО МУНИЦИПАЛЬНОГО РАЙОНА